Construction Step 7 - June 2011 to July 2011
Click here or on the image for a detailed .pdf of Step 7
Traffic and temporary alignments:
Woodmen Road traffic shifted to new bridge Complete
Turning movements restricted for 14 days to allow for completion of ramps
- Westbound and eastbound Woodmen Road
to northbound Academy Boulevard Complete
- Southbound Academy Boulevard to eastbound
and westbound Woodmen Road Complete
Key activities:
Complete ramps at northeast and northwest quadrant of intersection using fast-track construction (day and night work) Complete
Remove westbound Woodmen Road temporary alignment Complete
Restore Woodmen Commons Shopping Center parking lot 90%
Milestone:
Woodmen traffic shifted onto new bridge Complete - Milestone reached!
All construction step dates are subject to change and conditional upon resources and weather.
Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.