Construction Step 6 - September 2010 to June 2011
Click here or on the image for a detailed .pdf of Step 6
Traffic and temporary alignments:
Academy Boulevard traffic shifted to final alignment. Woodmen Road traffic remained on temporary alignment.
Key activities:
Remove Academy Boulevard temporary alignment. Complete
Complete Woodmen Road bridge embankment at west end of bridge. Complete
Construct retaining walls in SW quadrant of intersection. Complete
Woodmen Road paving east of Academy Boulevard. Complete
Milestone:
Construction of Earl Drive between Academy Boulevard and
York Road. Complete - Milestone Reached
All construction step dates are subject to change and conditional upon resources and weather.
Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.