Construction Step 5 April 2010 to September 2010
Click here or on the image for a detailed .pdf of Step 5
Traffic and temporary alignments:
Academy Boulevard traffic remained on Academy
temporary alignment. Woodmen Road traffic shifted
to temporary alignment
Key activities:
Excavate for Academy Boulevard final alignment. Complete
Complete structural concrete on Woodmen Road Bridge. Complete
Construct embankment at east end of bridge, and retaining walls in southeast quadrant of intersection. Complete
Install storm drain on Academy Boulevard. Complete
Milestone:
Installation of 42-inch water line complete. Complete -
Milestone Reached
All construction step dates are subject to change and conditional upon resources and weather.
Two lanes on Woodmen and three lanes on Academy will be open during peak traffic hours. All businesses are open for your patronage.