Construction Step 4
Click here or on the image for a detailed .pdf of Step 4
Traffic and temporary alignments:
Academy Boulevard traffic shifted onto Academy temporary alignment.
Woodmen Road traffic remained on existing roadway alignment.
Key activities:
Construct detention ponds on east end of project area. Complete
Install storm drains (throughout project area).Complete
Continue 42-inch water line under Academy Boulevard. Complete
Begin excavation on Academy Boulevard. Complete
All construction step dates are subject to change and conditional upon resources and weather.